Burwell Solar
East England · Solar · Operating
Output history
Reported availability
Unit lifecycle and sources
| BM unit | Technology | Registered capacity | Current lifecycle |
|---|---|---|---|
| BRCHS-1 | Solar | 50 MW | Operating — dated evidence |
Sourced events
- 19 Sept 2026 · BRCHS-1
EDF identifies the operational Burwell site connected directly to the National Grid substation and states 49.8 MW generating capacity. The committed crosswalk ties BRCHS-1 to Burwell 11 Solar Ltd and this project. The 49.8 MW AC generating denominator is used for metered output; DUKES' 69.9 MW PV installed figure is retained as a different likely DC/module basis, and the 50 MW registry reference remains separate.
Source date: 2026-09-19 · Reviewed: 2026-09-19
Primary source (opens in a new tab)
Physical capacity evidence
BRCHS-1 · 49.8 MW · evidenced from 2026-09-19
EDF identifies the operational Burwell site connected directly to the National Grid substation and states 49.8 MW generating capacity. The committed crosswalk ties BRCHS-1 to Burwell 11 Solar Ltd and this project. The 49.8 MW AC generating denominator is used for metered output; DUKES' 69.9 MW PV installed figure is retained as a different likely DC/module basis, and the 50 MW registry reference remains separate.
Source 2026-09-19 · reviewed 2026-09-19
Operator capacity sourceWhole-site registered total: 50 MW, including retired units.
Registered capacity is the value retained in the committed BM-unit source snapshot. “Not retained” means the registry no longer supplied a positive figure; it does not mean the unit historically had no capacity. If a unit with a retirement event publishes a non-zero live declaration, the live declaration keeps it in the operating fleet pending review.
About this asset
Burwell Solar is a operating solar site in East England. It has 1 non-retired (0 unverified) and 0 retired mapped Balancing Mechanism unit, with 50 MW on the displayed capacity basis.
The source catalogue has no site coordinate, so the explorer shows a regional position rather than an exact location.
Current output is the operator’s declared Physical Notification. Metered output is published later and is shown as the solid portion of the history chart; outage shading comes from REMIT notices.