South Scotland · Wind · Operating

Lifecycle
Operating
Declared output
—
Sourced installed capacity
19 MW
Declared utilisation
—

Output history

Unavailable because this deployment has no stored history for that range.

Reported availability

REMIT unavailability affecting this station over the last 12 months.

Unit lifecycle and sources

Effective-dated status is applied before station capacity and technology are calculated.
BM unitTechnologyRegistered capacityCurrent lifecycle
TRLGW-1Wind19 MWOperating — dated evidence

Sourced events

  1. 1 Sept 2020 · TRLGW-1

    The current developer page reports that Tralorg was commissioned in August 2020 with up to 18.8 MW installed capacity. TRLGW-1 is the sole mapped generation BMU. Evidence begins after the stated commissioning month. The eight turbines' individual maximum rating of 2.5 MW and REPD's 20 MW describe the upper design sum, not the operator's as-built site rating; the 18.7 MW registry reference remains separate.

    Source date: 2026-09-19 · Reviewed: 2026-09-19

    Primary source (opens in a new tab)

Physical capacity evidence

TRLGW-1 · 18.8 MW · evidenced from 2020-09-01

The current developer page reports that Tralorg was commissioned in August 2020 with up to 18.8 MW installed capacity. TRLGW-1 is the sole mapped generation BMU. Evidence begins after the stated commissioning month. The eight turbines' individual maximum rating of 2.5 MW and REPD's 20 MW describe the upper design sum, not the operator's as-built site rating; the 18.7 MW registry reference remains separate.

Source 2026-09-19 · reviewed 2026-09-19

Operator capacity source

Whole-site registered total: 18.7 MW, including retired units.

Registered capacity is the value retained in the committed BM-unit source snapshot. “Not retained” means the registry no longer supplied a positive figure; it does not mean the unit historically had no capacity. If a unit with a retirement event publishes a non-zero live declaration, the live declaration keeps it in the operating fleet pending review.

About this asset

Tralorg is a operating wind site in South Scotland. It has 1 non-retired (0 unverified) and 0 retired mapped Balancing Mechanism unit, with 19 MW on the displayed capacity basis.