| BM unit | Technology | Registered capacity | Current lifecycle |
|---|---|---|---|
| AFTOW-1 | Wind | 50 MW | Operating — dated evidence |
Sourced events
- 17 Oct 2018 · AFTOW-1
Red Rock announces its purchase of the operational 50 MW Afton farm. The Power Station Dictionary maps its sole generation unit to AFTOW-1. Evidence begins the next complete UTC day after publication; no exact September commissioning day is inferred.
Source date: 2018-10-16 · Reviewed: 2026-09-13
Primary source (opens in a new tab)
Physical capacity evidence
AFTOW-1 · 50 MW · evidenced from 2018-10-17
Red Rock announces its purchase of the operational 50 MW Afton farm. The Power Station Dictionary maps its sole generation unit to AFTOW-1. Evidence begins the next complete UTC day after publication; no exact September commissioning day is inferred.
Source 2018-10-16 · reviewed 2026-09-13
Operator capacity sourceWhole-site registered total: 50 MW, including retired units.
Registered capacity is the value retained in the committed BM-unit source snapshot. “Not retained” means the registry no longer supplied a positive figure; it does not mean the unit historically had no capacity. If a unit with a retirement event publishes a non-zero live declaration, the live declaration keeps it in the operating fleet pending review.
About this asset
Afton is a operating wind site in South Scotland. It has 1 non-retired (0 unverified) and 0 retired mapped Balancing Mechanism unit, with 50 MW on the displayed capacity basis.
Published site coordinate.
Current output is the operator’s declared Physical Notification. Metered output is published later and is shown as the solid portion of the history chart; outage shading comes from REMIT notices.