Bhlaraidh Windfarm 1
North Scotland · Wind · Operating
Output history
Reported availability
Unit lifecycle and sources
| BM unit | Technology | Registered capacity | Current lifecycle |
|---|---|---|---|
| BHLAW-1 | Wind | 108 MW | Operating — dated evidence |
Sourced events
- 8 Jun 2020 · BHLAW-1
Operating by the dated operator publication; this is an evidence boundary, not a commissioning timestamp or a live availability observation. The report identifies the original Bhlaraidh farm, mapped to BHLAW-1. The proposed Bhlaraidh Extension is excluded. Evidence begins at the report launch date, not an inferred 2017 commissioning day.
Source date: 2020-06-08 · Reviewed: 2026-09-13
Primary source (opens in a new tab)
Physical capacity evidence
BHLAW-1 · 108 MW · evidenced from 2020-06-08
The report identifies the original Bhlaraidh farm, mapped to BHLAW-1. The proposed Bhlaraidh Extension is excluded. Evidence begins at the report launch date, not an inferred 2017 commissioning day.
Source 2020-06-08 · reviewed 2026-09-13
Operator capacity sourceWhole-site registered total: 108 MW, including retired units.
Registered capacity is the value retained in the committed BM-unit source snapshot. “Not retained” means the registry no longer supplied a positive figure; it does not mean the unit historically had no capacity. If a unit with a retirement event publishes a non-zero live declaration, the live declaration keeps it in the operating fleet pending review.
About this asset
Bhlaraidh Windfarm 1 is a operating wind site in North Scotland. It has 1 non-retired (0 unverified) and 0 retired mapped Balancing Mechanism unit, with 108 MW on the displayed capacity basis.
Published site coordinate.
Current output is the operator’s declared Physical Notification. Metered output is published later and is shown as the solid portion of the history chart; outage shading comes from REMIT notices.