90 MW
Declared utilisation
—

Output history

Unavailable because this deployment has no stored history for that range.

Reported availability

REMIT unavailability affecting this station over the last 12 months.

Unit lifecycle and sources

Effective-dated status is applied before station capacity and technology are calculated.
BM unitTechnologyRegistered capacityCurrent lifecycle
BOWLW-1Wind90 MWOperating — dated evidence

Sourced events

  1. 24 Jun 2008 · BOWLW-1

    The ministerial answer lists Barrow as an operational 90 MW wind farm, attributing the inventory to the British Wind Energy Association. The dictionary maps BOWLW-1 to this site; the operator also confirms 30 turbines totalling 90 MW. Evidence starts after publication, not at an invented 2006 commissioning day.

    Source date: 2008-06-23 · Reviewed: 2026-09-13

    Primary source (opens in a new tab)

Physical capacity evidence

BOWLW-1 · 90 MW · evidenced from 2008-06-24

The ministerial answer lists Barrow as an operational 90 MW wind farm, attributing the inventory to the British Wind Energy Association. The dictionary maps BOWLW-1 to this site; the operator also confirms 30 turbines totalling 90 MW. Evidence starts after publication, not at an invented 2006 commissioning day.

Source 2008-06-23 · reviewed 2026-09-13

Operator capacity source

Whole-site registered total: 90 MW, including retired units.

Registered capacity is the value retained in the committed BM-unit source snapshot. “Not retained” means the registry no longer supplied a positive figure; it does not mean the unit historically had no capacity. If a unit with a retirement event publishes a non-zero live declaration, the live declaration keeps it in the operating fleet pending review.

About this asset

Barrow Offshore Windfarm is a operating wind site in North West England. It has 1 non-retired (0 unverified) and 0 retired mapped Balancing Mechanism unit, with 90 MW on the displayed capacity basis.

Published site coordinate (offshore).

Current output is the operator’s declared Physical Notification. Metered output is published later and is shown as the solid portion of the history chart; outage shading comes from REMIT notices.