Hunterston Generator

South Scotland · Nuclear · Retired

Lifecycle
Retired
Declared output
Retired
Sourced installed capacity
None
Declared utilisation
—

Output history

Unavailable because this deployment has no stored history for that range.

Unit lifecycle and sources

Effective-dated status is applied before station capacity and technology are calculated.
BM unitTechnologyRegistered capacityCurrent lifecycle
HUNB-7Nuclear510 MWRetired from 27 Nov 2021
HUNB-8Nuclear510 MWRetired from 8 Jan 2022

Sourced events

  1. 8 Jan 2022 · HUNB-8

    EDF dates Reactor 4 cessation to midday on 7 January 2022. Its October 2014 stakeholder report explicitly joins Reactor 4 to Turbine Generator 8. Applied from the next complete UTC day. Supporting identity source: https://www.edfenergy.com/sites/default/files/hnb_october_2014.pdf

    Source date: 2022-01-07 · Reviewed: 2026-09-13

    Primary source (opens in a new tab)
  2. 27 Nov 2021 · HUNB-7

    EDF dates Reactor 3 cessation to 26 November 2021. ONR report ONR-OFD-PAR-18-031 identifies its Turbine Generator 7; the dictionary maps HUNB-7 to Hunterston B. Applied from the next complete UTC day, separately from Reactor 4. Supporting identity source: https://www.onr.org.uk/media/41opfv2u/hunterston-b-18-031.pdf

    Source date: 2022-03-17 · Reviewed: 2026-09-13

    Primary source (opens in a new tab)

Physical capacity evidence

Whole-site registered total: 1020 MW, including retired units.

Registered capacity is the value retained in the committed BM-unit source snapshot. “Not retained” means the registry no longer supplied a positive figure; it does not mean the unit historically had no capacity. If a unit with a retirement event publishes a non-zero live declaration, the live declaration keeps it in the operating fleet pending review.

About this asset

Hunterston Generator is a retired nuclear site in South Scotland. It has 0 non-retired (0 unverified) and 2 retired mapped Balancing Mechanism units.

Published site coordinate.

Current output is the operator’s declared Physical Notification. Metered output is published later and is shown as the solid portion of the history chart; outage shading comes from REMIT notices.