Glendoe

North Scotland · Hydro · Operating

Lifecycle
Operating
Declared output
—
Sourced installed capacity
100 MW
Declared utilisation
—

Output history

Unavailable because this deployment has no stored history for that range.

Reported availability

REMIT unavailability affecting this station over the last 12 months.

Unit lifecycle and sources

Effective-dated status is applied before station capacity and technology are calculated.
BM unitTechnologyRegistered capacityCurrent lifecycle
GLNDO-1Hydro100 MWOperating — dated evidence

Sourced events

  1. 15 Jul 2014 · GLNDO-1

    SSE describes its operating 100 MW Glendoe hydro scheme on 14 July 2014. The dictionary maps GLNDO-1 to Glendoe. Evidence begins the next complete UTC day; the earlier 2009 tunnel failure and 2012 restart are not an uninterrupted operating or capacity history. Other small schemes listed on the modern Glendoe page are excluded.

    Source date: 2014-07-14 · Reviewed: 2026-09-13

    Primary source (opens in a new tab)

Physical capacity evidence

GLNDO-1 · 100 MW · evidenced from 2014-07-15

SSE describes its operating 100 MW Glendoe hydro scheme on 14 July 2014. The dictionary maps GLNDO-1 to Glendoe. Evidence begins the next complete UTC day; the earlier 2009 tunnel failure and 2012 restart are not an uninterrupted operating or capacity history. Other small schemes listed on the modern Glendoe page are excluded.

Source 2014-07-14 · reviewed 2026-09-13

Operator capacity source

Whole-site registered total: 100 MW, including retired units.

Registered capacity is the value retained in the committed BM-unit source snapshot. “Not retained” means the registry no longer supplied a positive figure; it does not mean the unit historically had no capacity. If a unit with a retirement event publishes a non-zero live declaration, the live declaration keeps it in the operating fleet pending review.

About this asset

Glendoe is a operating hydro site in North Scotland. It has 1 non-retired (0 unverified) and 0 retired mapped Balancing Mechanism unit, with 100 MW on the displayed capacity basis.

Published site coordinate.

Current output is the operator’s declared Physical Notification. Metered output is published later and is shown as the solid portion of the history chart; outage shading comes from REMIT notices.